You should come and check out our factory sometime!

For the last 2 years we have been manufacturing using a moving production line. Every building moves through 11 ‘Stations’ within our factory.

Each ‘Station’ has all the tools and materials required for the trades to do their portion of their work before it moves on to the next ‘Station’.  The 11 steps of the process are:

  1. Chassis, Flooring and Wall Framing
  2. Roof , Plumbing & Electrical Rough In
  3. Plasterboard Sheeting, Window Install
  4. Plasterboard Setting, Waterproofing
  5. Cornice and Plasterboard Sanding
  6. Fixout, Cladding and Kitchen Install
  7. Painting
  8. Painting
  9. Tiling
  10. Tiling/Electrical Fitout
  11. Plumbing Fitout and Cleaning

Each station requires 1½ days – meaning from start to finish takes 16½ days. It also means we produce a fully finished and furnished cabin every 1½ days. Pretty quick!

 